Labour Cost Calculator

Enter the quantity, the labour time per unit (or a crew size and its output per hour), the efficiency and the wage. Add regular hours, an overtime premium and employer on-costs to see the full labour cost of the job and per unit.

How do you know the labour time?

Person-minutes: 2 people for 3 minutes = 6.

100 = the team works at the standard time. 80 = it takes 25% longer.

Benefits and contributions you pay on top of wages, at your own rates.

Total person-hours before overtime starts. Empty = no overtime.

Extra on the hourly wage: 50 for time-and-a-half, 100 for double. Use the rate that applies to you.

Shows how many worker-shifts the job needs.

Formulas used

  • standard hours = units × standard minutes per unit ÷ 60 (or units × crew size ÷ crew output per hour)
  • labour hours = standard hours ÷ (efficiency % ÷ 100)
  • overtime hours = labour hours − regular hours available (if more)
  • wages = regular hours × wage + overtime hours × wage × (1 + premium % ÷ 100)
  • total = wages × (1 + on-costs % ÷ 100); cost per unit = total ÷ units

Overtime premiums and employer contributions are set by law and contracts that differ by country, so no rates are built in: type your own costs, wages and percentages. Results are rounded for display only; the calculation keeps full precision.

Pricing the people time in a production job

Direct labour is the work of the people who make, assemble or pack the product. This page starts from a standard time, adjusts it for how fast the team really works, and adds overtime and employer costs.

Two ways to enter the time

If you have a time study or routing, enter the standard person-minutes per unit. Two people working together for three minutes is six person-minutes. If instead you know that a crew of four packs 120 cartons an hour, choose crew output: each carton takes 4 ÷ 120 of an hour, two person-minutes.

Efficiency

Standards assume a trained team working at a normal pace. New staff, small batches and interruptions make jobs take longer. Labour efficiency converts standard hours into hours that will be paid: at 80%, a job worth 100 standard hours takes 125.

Overtime and on-costs

When the job needs more hours than you have at normal time, the extra hours are paid at a premium. Enter the regular person-hours available and the premium your contract or local law requires. Premiums and employer contributions vary between countries and agreements, so the page has no defaults for them. On-costs are what you pay on top of wages, such as pension or social security contributions and paid leave, entered as a percentage.

Worked example

A job of 1,000 units at 6 standard minutes each is 100 standard hours. At 80% efficiency that becomes 125 hours. Only 100 regular hours are available, so 25 hours are overtime at a 50% premium. With a wage of 100 an hour and 20% on-costs, the total is 16,500, or 16.50 per unit.

When to use a fuller employee cost

If you need the hourly rate itself, including holidays and benefits spread over the year, work it out first and type it in as the wage with on-costs set to zero. Indirect staff such as supervisors belong in overhead, which you can add in the production cost calculator.

How to use Labour Cost Calculator

  1. Choose minutes per unit or crew output per hour, and enter the quantity.
  2. Enter the labour efficiency and the wage per hour.
  3. Optionally add regular hours, the overtime premium, on-costs and shift length, then read the cost per unit.

Privacy: how it works

Calculations run in your browser. The amounts you enter are not sent anywhere.

Frequently asked questions

How is labour cost per unit calculated?

Labour hours = units × standard minutes ÷ 60 ÷ efficiency. Multiply by the wage, add the overtime premium on hours above the regular hours and your on-costs, then divide by units.

What does labour efficiency do?

It turns the standard time into the time the job really takes. At 80% efficiency, 100 standard hours take 125 hours to complete.

Which overtime rate should I use?

The one in your employment law or contract. Rules differ by country and industry, so the calculator does not assume a rate. Enter 50 for time-and-a-half or 100 for double pay.