Material Requirement Calculator
Enter how many finished units you need and the materials in one unit. The calculator adds the extra for yield and scrap, takes off what you already have or have ordered, rounds up to whole packs and prices the order.
100 if every unit started passes. 95 starts about 5.3% more units.
Formulas used
units to start = finished units ÷ (yield % ÷ 100)gross need = quantity per unit × units to start ÷ (1 − scrap % ÷ 100)net need = gross need − on hand − on order (never below 0)order quantity = ⌈net need ÷ pack size⌉ × pack size
This is a single-level bill of materials. For sub-assemblies, work out their quantity first and run them as a separate list. Lead times and safety stock are not included.
Working out what to buy for a production order
Before a job starts, someone has to check that every material is there in the right quantity. Doing it by hand for a long bill of materials invites mistakes, especially once scrap allowances, stock already on the shelf and open purchase orders are involved. This page does the explosion for one level of the bill.
Start from finished units
Enter how many good finished units the order needs. If not every unit started passes final inspection, enter the finished-goods yield: at 95%, an order for 950 needs 1,000 started. Every material quantity is then based on the units started, not the units shipped.
Gross requirement
For each material, multiply the quantity in one unit by the units to start. Then allow for processing loss. If 5% of the sheet issued ends up as offcuts, the quantity is divided by 0.95, so 0.95 square metres per unit across 1,000 units becomes 1,000 square metres issued.
Net requirement
Take off free stock on hand and quantities already ordered that will arrive in time. If 200 square metres are in the store and 100 more are on order, 700 still need to be bought. A material already covered by stock shows zero.
Packs and price
Suppliers sell in rolls, bags, boxes or minimum lots. Enter the pack size to round the order up to whole packs. Add the cost per unit of the material to price each order line and the total.
Things to check
Stock on hand should be free stock, not material already reserved for another job. Quantities on order count only if they arrive before you need them. The page does not handle multi-level bills of materials, lead times or safety stock. For a sub-assembly, work out its quantity first and run its parts as a second list. After the job, compare what was really used with the material consumption calculator.
Units
Keep each material in one unit of measure throughout: if the bill says grams, enter stock and pack size in grams too.
How to use Material Requirement Calculator
- Enter the finished units needed and the finished-goods yield.
- List each material with its quantity per unit, scrap %, stock on hand and quantity on order.
- Add pack sizes and costs if you want, then read the order quantities and download the table.
Privacy: how it works
Calculations run in your browser. The figures you enter are not sent anywhere.
Frequently asked questions
What is the difference between gross and net requirement?
Gross requirement is everything the job needs, including scrap. Net requirement is what is left to buy after stock on hand and open orders are taken off.
How are scrap and yield applied?
Yield raises the number of units started (950 good at 95% yield means 1,000 started). Scrap raises each material: quantity ÷ (1 − scrap %).
Does it handle sub-assemblies?
It works on one level of the bill of materials. Work out the sub-assembly quantity first, then run its materials as a separate list.